Bill a project by percentage of completion
Objective. Invoice each project phase from its cumulative percentage of completion, deduct amounts already invoiced and preserve a clear reconciliation between the contract budget, progress and issued invoices.
What you will learn
- Structure the billing budget into stable, identifiable project phases.
- Calculate the current invoice from cumulative completion rather than the period-only percentage.
- Understand how previous invoices and a decrease in progress affect the amount to bill.
Recommended workflow
- Create the phase budget with consistent sales codes, descriptions, amounts and VAT rules.
- Open the dedicated progress-billing workflow for the correct client and matter.
- Enter documented cumulative completion for each phase and review the previously invoiced amount.
- Verify the difference to invoice, the draft and its appendix, then reconcile the new cumulative total after issue.
Checks before continuing
- The sum of phase budgets matches the contractual billing basis.
- Each completion percentage is supported by an approved business source.
- A negative difference is reviewed as a potential credit note and is never validated automatically.